Monday, October 24, 2011
Pumpkins and sunshine at HVRM 10/22/11
Saturday, October 15, 2011
Track Gang Rips Up Arlington Crossing on a 60 Degree Day 15 Oct 2011
Georgeous day at North Judson, in the 60's, breezy fall day, clear blue sky. Perfect for an outside
project.
I arrived al little before 10am, quiet around the depot as the only train of the day would
be at 1:30pm to La Crosse. All you could hear was the farm combines in the nearby
corn fields. Getting ready, I head down to the Arlington St crossing. Cory has made quick
work of the rotten timbers, as not one came out intact. A detailed inspection of the ties
revealed 8 needed replacing. A rail joint needed new bolts, the sun warmed the rail
to close the gap, but will need the C&I track crew to drill out 3 bolt holes to finish the
rail joint. Eight new ties were put in in along with tamping and spiking. The tourist train
past twice without a problem. The North Judson city street dept came down earlier in
the week and cut the pavement. Bing manned his Bobcat along with faithful dog companion
to keep Bing awake. John, Dave, Grandson Seth, Joe, Bob, Mark and Jason Jordan all manned
shovels thru the day.
Mark, during the week has repainted the PC boxcar into Tuscan Red PRR paint. Nice job.
Joe has been working on the NKP bay window caboose during the week getting it ready
for a new paint job.
The 1:30pm La Crosse train left a little off schedule, but had over 170 riders today.
Nice crowd.
Have a nice week, Les will be back next weekend, I will be gone on vacation.
Tom
http://hoosiervalleyrestorationpage.blogspot.com/
Link to HVRM Blog
project.
I arrived al little before 10am, quiet around the depot as the only train of the day would
be at 1:30pm to La Crosse. All you could hear was the farm combines in the nearby
corn fields. Getting ready, I head down to the Arlington St crossing. Cory has made quick
work of the rotten timbers, as not one came out intact. A detailed inspection of the ties
revealed 8 needed replacing. A rail joint needed new bolts, the sun warmed the rail
to close the gap, but will need the C&I track crew to drill out 3 bolt holes to finish the
rail joint. Eight new ties were put in in along with tamping and spiking. The tourist train
past twice without a problem. The North Judson city street dept came down earlier in
the week and cut the pavement. Bing manned his Bobcat along with faithful dog companion
to keep Bing awake. John, Dave, Grandson Seth, Joe, Bob, Mark and Jason Jordan all manned
shovels thru the day.
Mark, during the week has repainted the PC boxcar into Tuscan Red PRR paint. Nice job.
Joe has been working on the NKP bay window caboose during the week getting it ready
for a new paint job.
The 1:30pm La Crosse train left a little off schedule, but had over 170 riders today.
Nice crowd.
Have a nice week, Les will be back next weekend, I will be gone on vacation.
Tom
http://hoosiervalleyrestorationpage.blogspot.com/
Link to HVRM Blog
Sunday, October 9, 2011
Pumpkin Trains
Kudos to all the individual members and family members who worked so hard to make yesterday's Pumpkin Trains a great success. There were over 407 riders with 276 pumpkins sold. Smiling facing lugging pumpkins down the crowded platform was a wonderful sight to see!
The day started out with the repair of the Nickel Plate open-air car which was greatly appreciated with the beautiful weather. The pumpkins were delivered and scattered throughout the grassy area for each of the trains. The train crew, car hosts, flaggers, track crew, gift shop workers, ticket sellers and punchers all worked diligently throughout the day. The clean-up crew at the end of the day made the depot and outdoor area ready for next weekend.
Thanks to one and all, whether you helped out for a few hours or all day!
Loretta
Loretta
Loretta Kosloske
Marketing Specialist
Hoosier Valley Railroad Museum
North Judson, In 46366
219-395-0369 (cell)
219-996-6687 (home)
Pumkin Trains at HVRM on a WONDERFUL DAY 8 OCT 2011
Greetings to all Pumpkin Pickers
A great day Saturday 8 October was had by all at HVRM. Loretta confirmed that over 400
riders on the pumpkin trains and 275 pumpkins sold. Temps in the upper 70's, clear
blue skies, a perfect fall day. The local farmers were busy havesting corn and beans
up and down the C&I line.
Arriving at 8am, John LaOrange had the Erie 310 running an on the move. He moved
on down track 1 and hooked up to the NKP open air car, moving it to track 3. Cory and Dave
were ready with an air jack to lift the car up and change out the broken spring a truck.
Making quick work of lifting the weight off the truck, a track jack was positioned with a
steel rail joiner to lift the bolster taking the weight off the springs. A quick exchange
of springs and the jacks removed the car was set down on the bolster. It had moved
slightly, but a nudge got the center pin lined up and centered. NKP open air car back in
service for the pumpkin trains and it was filled to capacity on the first run.
I missed the board meeting, but was short.
Joe Kingsbury has scaffolding set up in the west shop on both sides of the NKP bay window
caboose. It looks as if the roof has been cleaned of old flaking paint and a fresh coat
of primer and black paint has been put down. Sides of the car have been sanded and getting
ready for paint. Joe will make quick work on this project.
I moved to the the REA trailer and setup my scaffolding. Getting set up was quick and
grinding commenced on the sides. . After a quick cleanup of prior work, primer was
applied quickly. Things moved quickly and I completed the south side and moved to the
north side. Running out of paint, break time for lunch and resupply of a gallon of primer.
I finished up at approx 2:30 and broke down for departure. Had to be home by 3:30pm
for a sports school charter.
On the way out, I made a quick trip to the east end, where the track crew gang was busy
cleaning up the paving project of the C&I crossing on main street, hauling away debris
and getting the shoulders filled. A super paving job was done last week and now makes
the crossing smooth as glass. Next weekend Arlington Street crossing will be taken
apart for paving the following Monday.
Mark Kniebel has been working on the soon to be PRR boxcar during the week, and the
manlift was positioned at the west end of the car about 1/3 done.
Mostly everyone was helping with the Pumpkin trains, so no other work was performed
on Saturday.
Tom
A great day Saturday 8 October was had by all at HVRM. Loretta confirmed that over 400
riders on the pumpkin trains and 275 pumpkins sold. Temps in the upper 70's, clear
blue skies, a perfect fall day. The local farmers were busy havesting corn and beans
up and down the C&I line.
Arriving at 8am, John LaOrange had the Erie 310 running an on the move. He moved
on down track 1 and hooked up to the NKP open air car, moving it to track 3. Cory and Dave
were ready with an air jack to lift the car up and change out the broken spring a truck.
Making quick work of lifting the weight off the truck, a track jack was positioned with a
steel rail joiner to lift the bolster taking the weight off the springs. A quick exchange
of springs and the jacks removed the car was set down on the bolster. It had moved
slightly, but a nudge got the center pin lined up and centered. NKP open air car back in
service for the pumpkin trains and it was filled to capacity on the first run.
I missed the board meeting, but was short.
Joe Kingsbury has scaffolding set up in the west shop on both sides of the NKP bay window
caboose. It looks as if the roof has been cleaned of old flaking paint and a fresh coat
of primer and black paint has been put down. Sides of the car have been sanded and getting
ready for paint. Joe will make quick work on this project.
I moved to the the REA trailer and setup my scaffolding. Getting set up was quick and
grinding commenced on the sides. . After a quick cleanup of prior work, primer was
applied quickly. Things moved quickly and I completed the south side and moved to the
north side. Running out of paint, break time for lunch and resupply of a gallon of primer.
I finished up at approx 2:30 and broke down for departure. Had to be home by 3:30pm
for a sports school charter.
On the way out, I made a quick trip to the east end, where the track crew gang was busy
cleaning up the paving project of the C&I crossing on main street, hauling away debris
and getting the shoulders filled. A super paving job was done last week and now makes
the crossing smooth as glass. Next weekend Arlington Street crossing will be taken
apart for paving the following Monday.
Mark Kniebel has been working on the soon to be PRR boxcar during the week, and the
manlift was positioned at the west end of the car about 1/3 done.
Mostly everyone was helping with the Pumpkin trains, so no other work was performed
on Saturday.
Tom
Saturday, October 1, 2011
A Super Saturday October 1st At HVRM
Greetings to all,
Just an absolute beautiful day that resulted in good weather versus the horrid wet, wild, windy
mood that existed all week long. Friday was the worst with wind whipping up 20 foot waves
on Lake Michigan with power outages everywhere in northwest Indiana. But the next 7 days
are good warm temps in the 70's.
Arriving at a late hour of 9:30am, much activity was already started. The Main Street
crossing was already under attack.....demolition is more the way things were going. Prior to my
arrival, the air compressor running the air ratchet tools had removed most of the big bolts
holding the planks down to the ties. Cory manning the backhoe was busy pulling up the crossing
planks in a manner allowing the payloader and Bob Cat with the forks tips to get under the
planks and take them to a pile across the road, stacking the planks in a neat pile. John L running
the payloader, Bing R using his skid loader, Joe K, Dave C, Mark K, busy clearing the ties of
debris and stones. Both the C&I main and siding were clear of planks by 11:30am. Time for
lunch.
Meanwhile the train crew was getting things ready for the crowds that were to ride the
1:30pm train to La Crosse and Wade Tower with the Monon Historical group. The train
was spotted at the depot loading platform by 12:30pm. Many riders were boarding early
to get a good seat in the LIRR coach or the open air car. The chair lift car got a good work-out
today with a couple of wheel chairs and others who could not climb steps into the cars.
The train left close to 1:30pm but a couple of last minute items had to be taken care of,
getting a radio to the rear end, whose radio battery went dead at the last minute.
By 1:00pm, I had got my tools together, electric cord plugged in to the new outlet on the
east end of the kitchen car, manlift started, with some help from Joe K working the choke
and it started. Moved the manlift into position on the south side of the PC, soon to be PRR
boxcar for some grinding and priming. I got a good section of the side done before the
return of the train from La Crosse.
The crossing crew had the town street dept cutting a nice cut across Main street for a much
neater cut-in with the paving crew coming Tuesday of next week. Cleanup of the old asphalt
lasted the greater portion of the afternoon. All is ready for next week. Any bets on if someone
might try going over the tracks before Sunday morning. One of the track circuit wires was
broken and the crossing lights will flash till repaired, so that may help prevent an accidental
crossing.
The train returned from La Crosse at 4:34pm, everyone exited quickly and departed shortly
after, the train crew quickly locked all the cars, and put the train back on the caboose
track. Everyone was gone by 5pm.
Next week, most likely at 8am, board meeting, 3 trains running, and on the 15th, work
will commence on the Arlington street crossing, as only 1 train will be running that day.
Enjoy the fall weather this coming week, see you next Saturday.
Tom Travis
Just an absolute beautiful day that resulted in good weather versus the horrid wet, wild, windy
mood that existed all week long. Friday was the worst with wind whipping up 20 foot waves
on Lake Michigan with power outages everywhere in northwest Indiana. But the next 7 days
are good warm temps in the 70's.
Arriving at a late hour of 9:30am, much activity was already started. The Main Street
crossing was already under attack.....demolition is more the way things were going. Prior to my
arrival, the air compressor running the air ratchet tools had removed most of the big bolts
holding the planks down to the ties. Cory manning the backhoe was busy pulling up the crossing
planks in a manner allowing the payloader and Bob Cat with the forks tips to get under the
planks and take them to a pile across the road, stacking the planks in a neat pile. John L running
the payloader, Bing R using his skid loader, Joe K, Dave C, Mark K, busy clearing the ties of
debris and stones. Both the C&I main and siding were clear of planks by 11:30am. Time for
lunch.
Meanwhile the train crew was getting things ready for the crowds that were to ride the
1:30pm train to La Crosse and Wade Tower with the Monon Historical group. The train
was spotted at the depot loading platform by 12:30pm. Many riders were boarding early
to get a good seat in the LIRR coach or the open air car. The chair lift car got a good work-out
today with a couple of wheel chairs and others who could not climb steps into the cars.
The train left close to 1:30pm but a couple of last minute items had to be taken care of,
getting a radio to the rear end, whose radio battery went dead at the last minute.
By 1:00pm, I had got my tools together, electric cord plugged in to the new outlet on the
east end of the kitchen car, manlift started, with some help from Joe K working the choke
and it started. Moved the manlift into position on the south side of the PC, soon to be PRR
boxcar for some grinding and priming. I got a good section of the side done before the
return of the train from La Crosse.
The crossing crew had the town street dept cutting a nice cut across Main street for a much
neater cut-in with the paving crew coming Tuesday of next week. Cleanup of the old asphalt
lasted the greater portion of the afternoon. All is ready for next week. Any bets on if someone
might try going over the tracks before Sunday morning. One of the track circuit wires was
broken and the crossing lights will flash till repaired, so that may help prevent an accidental
crossing.
The train returned from La Crosse at 4:34pm, everyone exited quickly and departed shortly
after, the train crew quickly locked all the cars, and put the train back on the caboose
track. Everyone was gone by 5pm.
Next week, most likely at 8am, board meeting, 3 trains running, and on the 15th, work
will commence on the Arlington street crossing, as only 1 train will be running that day.
Enjoy the fall weather this coming week, see you next Saturday.
Tom Travis